I have the following table and I would like to make a representative chart.
Start End Duration
Implementation of project 01/05/2012 30/04/2014 24
XRD and Polymerisation 01/05/2012 01/06/2012 1
DFT 01/05/2012 01/11/2012 6
Supervision 01/09/2012 01/03/2014 18
Fund raising 01/02/2013 01/03/2014 13
Proposal writing 01/02/2013 01/03/2014 13
Conferences 01/12/2013 30/04/2014 5
Future post 01/11/2013 30/04/2014 6
Can you help me to make a nice chart?